    The Medan Jaya–Jalan Tun Hussein Onn flyover in Bintulu is now targeted for completion in July 2027, with physical progress at 89.05%. The latest project update said the work had received three extensions because of construction-site issues, including utility relocation. A major access problem involving the Bintulu district police headquarters has since been resolved, while the contractor has committed to the July target. The 2.6-kilometre package covers upgrades to the surrounding roads, a four-lane two-way flyover and improvements at the Medan Jaya and Taman Tinggi junctions. The finished project is expected to improve peak-hour traffic flow, comfort and safety. July 2027 is a completion target, not an immediate opening promise. Drivers will still need to follow traffic management arrangements and wait for the remaining works and final handover to be completed.