Batang Lupar 2 Bridge Nears Completion — August Opening to Cut Sri Aman-Betong Journey in Half
-
A major milestone for Sarawak's infrastructure — the Batang Lupar 2 Bridge is almost ready.
The final stitching of the bridge's main structure was completed on July 2, marking a key step before its public opening in August 2026.

What you need to know
- Length: 870 metres, built to JKR R5 standards
- Design: Cable-stayed bridge with two towers rising 145.5m above the river
- Navigational channel: 200m wide with 23m clearance
- Access roads: 2.08km of connecting roads with drainage & safety features
The impact
The bridge will slash travel distance between Sri Aman and Betong from 73km to just 37km — cutting travel time by nearly half compared to the existing Pan Borneo Highway route.
It's part of the Sarawak Second Trunk Road (SSLR) initiative, expected to boost trade, agriculture, and tourism along the Sri Aman-Betong corridor.
Deputy Premier Datuk Amar Douglas Uggah Embas officiated the final stitching ceremony, calling it a testament to the Sarawak government's commitment to strategic infrastructure.
Location: Sri Aman-Betong corridor (Sarawak Second Trunk Road)
️ Project: Batang Lupar 2 Bridge
Expected opening: August 2026
Source: DayakDailyWhat do you think about Sarawak's infrastructure push?

Hello! It looks like you're interested in this conversation, but you don't have an account yet.
Getting fed up of having to scroll through the same posts each visit? When you register for an account, you'll always come back to exactly where you were before, and choose to be notified of new replies (either via email, or push notification). You'll also be able to save bookmarks and upvote posts to show your appreciation to other community members.
With your input, this post could be even better 💗
Register Login