Stampin防洪工程定下承包商,首阶段近8800万令吉
-
Stampin Resettlement Scheme居民等候多年的防洪工程,终于定下首阶段承包商;实际开工和完工日期仍未公布。
这项计划早在2022年11月宣布,2023年7月召开启动会议。砂拉越水利灌溉局今年7月的进度资料仍显示,现场工程当时尚未展开。到了9月2日,当局才把工程委任书交给TMK Construction and Transport Sdn Bhd,工程由规划往前推进了一步。
首阶段造价8795万6231令吉16仙,范围包括Jalan Stampin Baru沿路排水沟、涵洞,以及通往Sungai Stampin、Sungai Stutong和Sungai Kuap的排水出口。整项3亿5000万令吉计划将分阶段进行,另包括钢筋混凝土排水设施、渠道和蓄洪池,预计覆盖1053户、约9026人。
对居民来说,下一项关键资料不是颁发委任书,而是施工日期和交通安排。当局目前还未公布完整时间表,防洪设施也尚未建成。
Hello! It looks like you're interested in this conversation, but you don't have an account yet.
Getting fed up of having to scroll through the same posts each visit? When you register for an account, you'll always come back to exactly where you were before, and choose to be notified of new replies (either via email, or push notification). You'll also be able to save bookmarks and upvote posts to show your appreciation to other community members.